Print Friendly Page
General Motors (Central Foundry Division)

Cleanup Progress Update

Massena, St. Lawrence County, NY


U.S.Environmental Protection Agency   Spring 2016
template
 
By the Numbers
  • 23,000 tons of PCB-contaminated sediment dredged from the St.Lawrence River system (including 16,900 cubic yards of contaminated soil and sediment from Turtle Cove and the surrounding area)
  • 21,389 tons of scrap metal recycled
  • 502,228 tons of hazardous waste shipped off site
  • 2.6 tons of asbestos removed
  • 59,000 tons of contaminated (but not classified as hazardous) waste removed and disposed of
  • 21.2 million gallons of remedial wastewater treated since 2011
 
PDF Document Available
GM cleanup front page General Motors Cleanup Progress Update
Massena, St. Lawrence County, NY
U.S. Environmental Protection Agency Spring 2016
Click on the image to see the entire 8 page document. 4.88 MB




Saint Regis Mohawk Tribe Environment Division
http://www.srmtenv.org/index.php?spec=2016/04/sf-gm/general-motors-cleanup-update